• Log In
  • Sign Up
  • Events
  • Village
    • Updates
    • Contacts & Support
    • Board of Directors
    • Meetings & Minutes
    • Governing Documents
    • Base Map
    • Find My Address
  • Maintenance
    • Submit a Ticket
    • Locker Door Program
    • Scheduled Maintenance
    • Find a Pro
    • Paint Codes
  • Resort
    • Today at Jay
    • Benefits
    • Lost & Found
Jay Peak Village
  • Log In
  • Sign Up
  • Events
  • Village
    • Updates
    • Contacts & Support
    • Board of Directors
    • Meetings & Minutes
    • Governing Documents
    • Base Map
    • Find My Address
  • Maintenance
    • Submit a Ticket
    • Locker Door Program
    • Scheduled Maintenance
    • Find a Pro
    • Paint Codes
  • Resort
    • Today at Jay
    • Benefits
    • Lost & Found

© 2026 Jay Peak Village

Here’s the Plan

Plans set direction. Conditions set reality.

2026 Village Painting Plan POSTED

441- 448 ~ May 25- June 12
451- 458 ~ Jun 15- Jul 03
145 -148 ~ Jul 06- Jul 27
391- 398 ~ Aug 03 – Aug 21

2026 Village Roofing Plan POSTED

How to read this schedule:

• Dates may overlap to allow for deliveries, dumpsters, and staging.

• This allows crews to move directly to the next building without delay.

• Dates may shift due to weather, site conditions, or construction progress.

Updated March 30, 2026

Schedule:

V137–140: Apr 6 – May 1

V391–398: May 4 – May 29

V381–388: May 25 – Jun 19

V141–144: Jun 15 – Jul 3

V153–156: Jun 29 – Jul 17

V331–338: Jul 13 – Aug 14
V341–348: Jul 13 – Aug 14

Weather buffer: Aug 15 – Aug 23

V351–358: Aug 24 – Sep 18

V411–418: Sep 14 – Oct 9

V431–438: Oct 5 – Oct 30

2026 Village Garden Bed & Landscape Wrok

details to follow

2025 Village Painting Plan

May 19 to until June 15
Buildings: V125–128
Full exterior painting from top to bottom.
A carpenter will be on-site to perform necessary repairs as they arise.

On or around June 23 until July 20
Buildings: V351–358
Estimated 4-week timeline.
Includes full exterior painting and required exterior repairs.

On or around August 4 until August 22
Buildings: V133–136
Estimated duration: 3 weeks.
Includes necessary repairs and complete exterior painting.

On or around August 25 until September 1st
Buildings: V137–140
Painters anticipate extensive repairs before painting.
Estimated duration: 4 weeks.

2025 Village Roof Replacement Schedule

VSF6
June 9 to June 25, 2025
Roofing crews are scheduled to begin mid-week, the week of June 9, as they finish another job. Single-family homes like VSF6 typically take about 2.5 weeks to complete, weather permitting. As this project nears completion, part of the crew may begin work at buildings 311–320.


V311–315
June 16 to July 13, 2025
The crew is expected to arrive in this parking area around June 18. They may begin with either 311–315 or 316–320. These two buildings will be roofed almost simultaneously, with an estimated timeline of 5 weeks.

V316–320
June 16 to July 13, 2025
Same schedule as V311–315. See above.


V301–308
July 26 to September 15, 2025
Roofing is expected to begin the week of July 7 and finish by August 3. Work may overlap with VSF2.
Rental Pool units have already been placed “off market.” Privately rented units should notify guests of possible disruption.


VSF2
August 4 to August 21, 2025
Roofing is expected to begin July 14 and finish by month-end. If the crew finishes early at VSF6, work may start sooner.
This building is in the Rental Pool and will be offline during this period.


V125–128
September 8 to October 1, 2025
Roofing will begin around September 8th and take approximately three weeks. This work will overlap with the final stages of V301–308.
This project marks the transition of operations from North Village to South Village. One Rental Pool unit will be offline during this time.

2025 Front Garden Bed/Landscape Work

Garden Bed Restoration Project
We’ve launched a multi-phase garden bed restoration project across the Village to revitalize aging landscaping, improve drainage, and enhance the long-term beauty and health of the property.

This work includes:
– Stripping out overgrown or damaged beds
– Salvaging and replanting viable plant material
– Re-shaping bed contours and installing fresh landscaping fabric
– Addressing hidden issues like disconnected drainage pipes

In progress:
V117–120 completed
V121–124 completed
V109–112 completed
V301–308 landscape fabric, topsoil, plants and mulch
V137–140 landscape fabric, topsoil, plants and mulch
V391–398 landscape fabric, topsoil, plants and mulch
V331-338 in progress – one side stripped

Our crews are working section by section, prioritizing the heavily overgrown sloped garden beds while we have excavation equipment on site. They’re doing their best to minimize disruption while making sure each area receives the care it deserves.
Thank you for your patience and support as we bring new life to the Village gardens!

Archive – Completed Work

2024 Village Painting Completed:
V361-368 
V371-378
V153-156 
V129-132

2024 Village Roofs completed:
V117-120
V121-124
V201-202

2024 Village Snow Guard Rail Installation is completed:
V121-124
V109-112
V201-202 
V101-104

2023 Village Roofs completed:
VSF 1
VSF 3
VSF 5
V105-108
V113-116

2022 Village Roofs completed:
V101-104
V109-112

2022 Village Painting completed:
VSF5
V113-116
117-120
121-124